Projects Start and Finish Dates
Project Title 00-01 01-02 02-03 03-04 04-05 05-06 06-07 07-08 08-09
General Classroom #1- Phase II 11/08/00 2/18/02
General Classroom #1 - Phase III 2/5/01 5/2/05
Three Classroom Buildings Dudley Hall Phase III 11/08/00 7/10/02
Three Classroom Buildings - Gibbs & CH Moore 11/09/00 7/30/07
Chemistry Laboratory 11/09/00 12/21/05
Cherry Hall Laboratory Building 01/08/03 6/24/09
Barnes Hall Laboratory 09/05/03   12/10/08
Graham Hall Engineering Lab 10/01/02 7/31/07
New Student Housing (Four Dormitories) 11/09/00 8/5/05
Morrison Residence Hall 10/01/02 1/3/05
Barbee Residence Hall 9/26/03 1/21/08
Harrison Auditorium 11/6/01 9/20/06
School of Agriculture Facilities 11/09/00 1/31/06
Corbett Intramural Addition 6/01/05 6/20/08
Hazardous & Waste Facility 11/09/00 5/5/05
Steam Lines & Manholes 11/2/01 8/28/02
New Education Building 1/15/04 2/29/08
Electrical Distribution System 11/09/00 5/14/04
Technology Infrastructure 11/08/01 12/13/05
Land Acquisition 01/03/01 7/5/06
Campus Security Lighting 11/08/00 1/10/03
  = Start
  = Finish