Home
NCA&TSU
Business&Finance
Engineer‘s Org Chart
Campus Map
Comments
Organizational Chart
University Engineer
Construction
HUB Vendor
Downloads
IMS Interface
About Us
Operations
Emergency
Work Request
Forms
Physical Plant
About Us
Property Management
:: Construction Update
:: Solicitations
:: Monthly Report
:: Bond Projects
:: Construction Aerial
:: Completed Projects
© 2008 NC A&T SU. Office of Facilities. All Rights Reserved.
General Classroom and Laboratory Complex - $29,920,700
Completed
General Classroom - Phase III - $7,157,675
Completed
Three Classroom Buildings (Dudley Phase III) Renovation - $1,200,000
Completed
Three Classroom Buildings (Gibbs & C.H. Moore) Renovation - $3,597,000
Completed
Science Facility - Replacement for Hines Hall - $21,831,600
Completed
Cherry Hall Laboratory Building Renovation - $8,438,200
Under Construction
Barnes Hall Laboratory Renovation - $5,550,100
Under Construction
Graham Hall Engineering Laboratory Renovation - $5,782,200
Completed
Holland Residence Hall Renovation - $856,800
Completed
New Student Housing (Four Dormitories) - $33,426,700
Completed
Morrison Residence Hall Renovation - $3,701,100
Completed
Zoe Barbee Residence Hall Renovation - $3,693,800
Under Construction
Harrison Auditorium Renovation - $2,895,200
Completed
Improvements to School of Agriculture Facilities - $1,832,700
Completed
Corbett Intramural Center - Addition - $7,035,000
Under Construction
Hazardous Materials and Waste Storage Facility - $1,575,000
Completed
Replacement of Steam Lines and Access Holes - $1,568,300
Completed
New School of Education - $9,430,700
Under Construction
Electrical Substation System - Upgrade and Expansion - $2,256,800
Completed
Technology Infrastructure Expansion and Acquisition - $2,921,700
Completed
Land Acquisition - $6,300,000
Completed
Campus Security Lighting - $828,716
Completed
Total: $161,800,091
Bond Projects
Start and Finish Dates
Actual Contract Amounts
Summary Six Year CI